Tag: Change Management
Change Management
by dtowngamer on Feb.16, 2010, under Uncategorized
Project manager (PM):
Project manager should involve to design and develop change management system and monitor the system. It is important to communicate the necessity of change management process and follow the process irrespective of the urgency. The project manager has to use the negotiation skills to find a solution when asked to implement a change that might jeopardize the project’s ability to deliver to the triple constraints.
Sponsor:
Sponsor will validate that the requested changes and review the results to provide a feedback whether they are in line with the original intent of the project. The sponsor heads the change control board.
Project team members:
Avoid making unauthorized changes and report any discrepancies.
The following six steps explains the process after designing a change management system—
Step 1: Making a change to the project
During project execution making a change to the project is the natural part of the project development. The change requests can come from anyone; team members, clients, sponsors, even the PM. Change requests can also come from people outside of the project, including functional organizations, vendors, and so on. The change request usually has to do with a discrepancy in what is planned for the product of the project. Discrepancies can cover specific functions of the product.
Step 2: Reviewing the change request
The PM will guarantee that every person on the team, or at least each area of the team, is represented during this review. In addition, the PM needs to make sure that the intention of the change request is clear to the team members. The PM should facilitate discussion until all team members’ questions are resolved. For large or complex change requests, the PM might consider asking the requestor to attend the review meeting so they can answer team questions.
Step 3: Determining the work to implement the change
Step 4: Accumulating the required work
With the accumulated information about the change request the proper sequence of the tasks involved will be determined which could be a mini project schedule just for this change.
Step 5: Analyze the impact of the change
The change request could impact the project plan or the requirements or both. By performing a ‘what if’ scenario, it can be determined exactly where the change request can be inserted into the existing project schedule to calculate the new critical path and the total cost of the change request based on the work estimates provided by the team.
Step 6: Having an Impact on the three constraints (Time, Budget, and Quality)
The next step is to determine the impact of the change on the constraints to the project. If even one of the triple constraints is affected by the change request, the approval from the CCB is necessary.
Cited
Baca, Claudia(2005). Project Manager’s Spotlight on Change Management. Sybex
Taylor, James C (2008). “Chapter 10 – Understanding the Project Change Process”. Project Scheduling and Cost Control: Planning, Monitoring and Controlling the Baseline. J. Ross Publishing.